Table of Contents Table of Contents
Previous Page  140 / 186 Next Page
Information
Show Menu
Previous Page 140 / 186 Next Page
Page Background

140

1-877-765-9565

WWW.POLYLOK.COM

REINFORCED CONCRETE INSTALLATION INSTRUCTIONS

INSTALLATION INSTRUCTIONS FOR TRAFFIC LOAD BEARING APPLICATIONS

1. Determine location and length of required trench drain. Also

determine drain outlet location.

2. Lay out and excavate for the trench drain. Allow for a minimum of

6” on all sides and 6” on the bottom. (17.5” wide X 11.75” deep)

(see diagram 2)

3. Determine which style of outlet is to be used; end outlet or bottom

outlet. Excavate for drain outlet pipe.

4. If bottom outlet is to be used, use a 3 1/2” hole saw to cut the outlet

opening. If theend outlet is used do not cut the bottom outlets.

(see diagram 3)

5. Install end caps and/or outlets on determined ends. Assemble all

required sections together at grade level. Make sure all grates are

screwed in place. Attach outlet pipe to trench drain.

6. Using duct tape, cover all grate openings. Carefully place the

assembled trench drain into bottom of the trench.

7. Using temporary supports, bring drain up to within approximately

1” of grade. Center trench drain in trench.

8. Using #4 rebar, drive in 4 pieces of verticle rebar through the holes

on trench drain at each corner per section. Make sure rebar is inserted

deeply and tied to provide a firm footing and to prevent floating once

the concrete is poured.

9. Raise the trench drain so that the top of the drain is even with the

finish grade. Wire tie trench to rebar at the 4 corners of each section.

Be sure to wire tie above and below at each coner hole position. Check

drain elevation frequently while tying. (see diagram 5)

10. Wire tie #3 rebar loops to #4 verticle rebars. (see diagram 5)

11. Wire tie #4 horizontal rebars to #3 rebar loops at all intersections.

12. Wire tie remaining #3 rebar loops to #4 horizontal rebars. Space

evenly in between already tied #3 rebar loops at all intersections.

13. Cross tie #4 vertical rebars at all drain joints. (see diagram 4)

14. Check that trench drain is still at proper elevation. Also check that

drain outlet pipe is secured to trench drain and that it has required pitch.

15. Using a 5,000 psi air entrained concrete mix, pour concrete using

proper vibration and consolidation practices.

16. Trowel finish flush with top of trench drain and even with grade.

An edger tool may be used if desired.

17. After concrete begins to set, promptly remove all duct tape from

grates.

REFER TO INSTALLATION DIAGRAM ABOVE